AT&T · 2021 – Present

Agentic Microservices Modernization

80+ services3 months vs. 12 estimated2-4 days to 4 hours70% automated
JavaSpring BootAgentic AIGitHub Copilot

Overview

Our team's application is composed of 80 microservices built on Java 8 and Spring Boot 2.x. With Spring Boot 2.x reaching end of life, staying on unsupported software was not an option. Java 8 was also EOL, so both had to be upgraded together. I led the effort to bring the entire service catalog up to supported versions.

This project had a second dimension to it: I used it as an opportunity to experiment with AI-assisted engineering and see how much of a large, repetitive migration could be automated.

The Challenge

Migration Scope vs. Manual Effort

Manual plan9-12 months
  1. 180+ services
  2. 2Repeated framework changes
  3. 3Service-by-service fixes
Automation target3 months
  1. 1Pattern discovery
  2. 2Prompted migrations
  3. 3Team parallelization

The original plan was to move to Java 21 and Spring Boot 4, the latest available versions. AT&T's security policies for offshore developers capped the supported Java version at 17, and the compatible Spring Boot version was 3.3. Since Spring Boot 4 requires Java 21 as its minimum, both targets had to come down together. Java 17 and Spring Boot 3.3 were the ceiling we could actually use.

Manual estimates put the effort at 9 to 12 months across 80 services. Each service required the same categories of changes: POM dependency updates, removal of deprecated APIs, and several framework-specific migration paths. No novel business logic was involved, just repetitive, well-documented work that developers across the industry had already done thousands of times. That made it a strong candidate for automation.

What I Built

Agentic Migration Workflow

Prompt Agents

POM

dependencies + Java target

AJSC

internal framework removal

API

javax to jakarta + date types

Docs

Swagger to springdoc

Service Workspace

One microservice

~70% automated

Copilot applies targeted migration prompts, then the remaining failures become reviewable fixes.

Verification Gates

Build
Start app
Smoke APIs
PR review

Feedback Memory

Missed-items log

Manual fixes were captured and fed into later prompt runs so the workflow improved service by service.

Before writing a single prompt, I manually upgraded two services to build a solid understanding of what actually needed to happen at each step. Then I spent two weeks researching and iterating on prompts using GitHub Copilot in VS Code.

My first attempt was a single prompt to handle the full upgrade. The results were inconsistent: sometimes the POM updated correctly, sometimes it did not. Also the service layer changes were unreliable. I broke the problem down into four targeted prompts, each scoped to one category of change.

The first prompt handled POM updates: bumping Java, Spring, and Spring Boot versions and replacing dependencies with compatible ones. I included my manually upgraded POM as a reference and explicitly called out fields the model consistently missed. The second prompt covered AJSC removal. AJSC was AT&T's internal framework for on-premises hosting. With the company now on Azure, AJSC was unsupported and incompatible with Java 17, so it needed to be replaced. The third prompt handled service layer deprecations: javax to jakarta, Date to LocalDateTime, and other API changes that Spring Boot 3.x introduced. The fourth migrated Swagger from Springfox to springdoc-openapi, including annotation updates and the removal of the Docket configuration class.

The workflow for each service: run the prompts, review the output, build and start the app, fix any failures, run a few API calls to verify functionality, then move to the next service. AI handled about 70 percent of each upgrade consistently. I kept a shared markdown file where the team logged every manual fix the prompts missed. I fed it back into each prompt run as a list of previously missed items. This helped close some gaps, but getting from 70 to 100 percent would have required a level of fine-tuning that was not worth the investment.

I ran knowledge transfer sessions throughout so the team could work on services in parallel while I developed later prompts. I reviewed every PR and mentored developers through the manual fixes.

Outcome

Migration Results

9-12 months3 months

total modernization timeline

2-4 days4 hours

typical per-service upgrade

manual repetition70% automated

repeatable migration work

What was estimated at 9 to 12 months took 3 months. A per-service upgrade that used to take 2 to 4 days came down to 4 hours, with GitHub Copilot handling the bulk of the repetitive work. After we finished, I demo'd the workflow and shared the prompts with teams across AT&T. Three teams have since reached out to reuse them for their own migration efforts.